Characteristics of the construction of high-speed railway bridge moving formwork

Characteristics of the construction of high-speed railway bridge moving formwork

Page view
[Abstract]:
There is little temporary land for construction; there is basically no requirement for the construction period of the roadbed, and the requirements for terrain, geology, bridge height and other
advantage:
 
There is little temporary land for construction; there is basically no requirement for the construction period of the roadbed, and the requirements for terrain, geology, bridge height and other conditions are not high;
 
Less impact on the surrounding environment;
 
Disadvantages:
 
Construction progress is relatively slow;
 
The construction equipment costed once during construction is relatively high;
 
Bridge cast-in-place is affected by weather conditions in winter and rainy seasons.